Project Title |
Project Description |
Current Phase |
Addition to M.T. Carter Building | Construct new 13,600 GSF research for College of Agriculture | Final Completion |
Demolish/Replace Daniel Gym and Demolish Harris Hall | Construct new 175,000 GSF academic facility (Academic Commons) | Construction |
New Student Union | Construct addition to the Foster Hall Student Union and renovate existing building | Design |
Improve and Replace Technology Infrastructure | Replace classroom AV, Upgrade Fiber Network campuswide, and address environmental issues in E&G Network rooms |
Design |
Improve Infrastructure for Campus Safety, Security, Energy Reduction and System Reliability |
Security improvements include the perimeter fencing, additional guard stations, exterior/interior surveillance cameras, exterior LED lighting fixtures, card reader systems, & steam system upgrades |
Design |
Construct Admissions Building | Construct new 30,000 GSF building for Admissions & Institutional Advancement | Design |
Waterproof Campus Buildings | Waterproofing basements and providing improved drainage at 11 academic and administrative buildings |
Design |
Improve Heating, Air Conditioning and Ventilation Campuswide for Infectious Aerosol Control |
Renovations Heating Ventilating and Air Conditioning (HVAC) systems. Focus on increasing ventilation, filtration and humidity control. Improvements to include total system replacements, targeted replacements, retro commissioning and/or enhanced building automation controls |
Design |
Renovate Summerseat for Urban Agriculture Center | Renovate Summerseat Bldg; Construct new Pavilion, Food Demonstration Facility, & Greenhouse for College of Agriculture |
Design |
Improve Campuswide Drainage | This project addresses severe flooding/drainage problems. The Improve Campuswide Drainage project will repair erosion damage, provide outfall stabilization, convert select open water stormwater management facilities to usable land, and address the inadequacy of the current storm sewer infrastructure in the historic district of campus |
Design |
Reroof Academic and Administrative Buildings Campuswide | This project addresses roofing systems that have outlived their useful life including the full or partial replacement of roof systems several bldgs. |
Design |
Improve Access and Accessibility | These projects will address accessibility and code compliance; accessible entrances, sidewalks & curbs, modifying/adding restrooms & either replacing or adding elevators. |
Design |